Call Us: 604.856.4799
Request A Quote

Update – November 12

We are currently on schedule with the installation. Hallways 3 and 4 will be completed by the end of the day today and the stairs installation is targeted to complete by end of day tomorrow.

Update – November 5th

The installation has been going smoothly! Thank you for your patience while we have been working in your space.

We are about one day behind schedule at the moment. Our crew will continue working this week and be back on Monday to do the installation on the stairs.

Update – November 4th

We are currently waiting on a shipment of carpet to complete the stairwells and the carpet base. Unfortunately this carpet was delayed in production but is expected to arrive mid-end of next week. We will schedule the installation in the remaining areas as soon as possible.

« Previous Page 
WCFA ICC Greater Langley Chamber of Commerce Insurance Brokers Association CHOA Greater Vancouver Home Builders Association Better Business Bureau BCAOMA Aviva