Island Cove Installation Schedule

SCHEDULE UPDTE JULY 24:

Thank you to everyone for your patience while we work in your building. The remaining installation is scheduled as follows:

July 24: Installation on floor 3
July 25: Installation on floor 2
July 28: Threshold reinstallation 9am-12pm

Residents only need to stay home for threshold reinstallation if their threshold was removed. If you have reinstalled it yourself, you do not need to stay home for the morning.

SCHEDULE UPDATE JULY 17:

Some additional floor prep is needed and the schedule will adjust. Please see the revised schedule below:
 
July 18: Floor prep on floors 7 & 5  
July 19: Floor prep on floors 4 & 3 
July 21: Floor prep on floor 2, installation on floor 7
July 22: Installation on floor 5
July 23: Installation on floor 4
July 24: Installation on floor 3
July 25: Installation of floor 2 & threshold reinstalled on all floors (Access to all Units Required)
 
FLOOR PREP WORK WILL AFFECT ACCESS TO YOUR SUITE FOR 1-2 HOUR PERIODS. 
During installation and floor prep, patching compound and glue need time to set. Our team will knock on your door & tape it off when glue or cement are outside your door. Our team will be within talking distance on the floor they are working on to answer any questions. We recommend limiting the number of trips in and out if possible and using stairwells if access to the elevator is blocked. Please expect construction noises & odors from glue or cement. Consider moving noise-sensitive activities outside of business hours or to another location. Our working hours are 8am-5pm weekdays, 10am-4pm Saturday.
 

UPDATE: JULY 9:

To install the carpet underneath your front door threshold, we require access to your suite on Wednesday July 16th from 9am-12pm to remove the front door threshold and Friday July 25th from 9am-12pm to reinstall it. If you cannot be home to provide access during this time:

  1. Remove the threshold yourself prior to July 16th. They can easily be removed by removing the two screws with a drill or screwdriver. It can be reinstalled once the new carpet has been installed on your floor.
  2. Leave keys with the building manager or trusted neighbour

The proposed installation schedule is below. It is subject to change. Updates can be viewed on the QR code below or blog.mirafloors.com/island-cove

July 16-25th 2025

SCHEDULE HAS BEEN MODIFIED – SEE ABOVE UPDATE.

 


If you have any questions about thresholds or specific accessibility concerns, please contact Kelsey Shipley at 604-996-5461 or kelsey@mirafloors.com 

 

 