Sunny Lodge – Flooring installation schedule

UPDATE JUL 3RD:

Tile installation in the storage locker hallway and in front of unit 102 is on hold while the strata looks into some moisture concerns in the storage hallway. We will return once strata has confirmed the moisture issues have been addressed. Carpet installation is on track to finish July 4th. The installer may need to return on Monday to finish up the stairs.

Thank you for your patience & co-operation allowing us in your space.

UPDATE JUNE 25th:

The flooring schedule for Sunny Lodge has been revised as follows:

July 2 – July 8 2025

  • July 2: Removal of existing carpet 
  • July 2-4: Floor prep & leveling 
  • July 4, 7 & 8: Tile installation & grouting in storage locker hallway & in front of Unit 102
  • July 4: Floor prep & carpet installation on the rest of the 1st floor hallway
 

ACCESS TO ALL 1st FLOOR UNITS WILL BE REQUIRED ON JULY 4th 10am-1pm to remove & reinstall unit thresholds

STORAGE LOCKER HALLWAY WILL BE CLOSED JULY 3,4, 7 & 8. ALL OTHER AREAS OF THE 1ST FLOOR MAY HAVE ACCESS LIMITED FOR 4-6 HOUR PERIODS DURING TILE INSTALLATION & 2-3 HOUR PERIODS DURING CARPET INSTALLATION.

Thank you to everyone with your patience in this situation & allowing us to work in your space.

 

UPDATE JUNE 24th: Today our installer discovered that an incorrect adhesive was used that “superglues” the carpet to the subfloor & will be much stickier underfoot for residents once removed. If the correct carpet glue was used, it is usually not too sticky. We decide to push installation to a later date so we can have a larger crew in place to remove the carpet & encapsulate the adhesive residue quickly. This will minimize the amount of time residents are exposed to the sticky glue.

A new installation schedule will be confirmed on June 25th or June 26th

We thank you for your patience with this change.

UPDATE JUNE 23rd: Job start is delayed to Tues June 24th due to an installer illness. We do not expect any changes to the schedule below due to this delayed job start.

MIRA Floors & Interiors will be installing new carpet tile & ceramic tile on the 1st floor. Here is our proposed schedule of work. All updates will be posted as determined as work progresses on site.

ACCESS TO ALL 1st FLOOR UNITS WILL BE REQUIRED ON JULY 4th 10am-1pm to remove & reinstall unit thresholds

STORAGE LOCKER HALLWAY WILL BE CLOSED JUNE 24-27th & 30th. ALL OTHER AREAS OF THE 1ST FLOOR MAY HAVE ACCESS LIMITED FOR 4-6 HOUR PERIODS DURING TILE INSTALLATION & 2-3 HOUR PERIODS DURING CARPET INSTALLATION.

June 23 – July 5 2025

  • June 23: Removal of all carpet on 1st floor
  • June 24-25: Floor prep & leveling
  • June 25-27, 30: Tile installation & grouting in storage locker hallway & in front of Unit 102
  • July 2-4: Floor prep & carpet installation on the rest of the 1st floor hallway
 

Please use caution at all times to ensure your safety. Our installer will knock on affected doors in the morning before starting work to communicate a day-specific schedule prior to starting. Please do not step in any wet glue or cement.
Please expect loud construction noises in the hallway from June 23-30 & consider moving any noise-sensitive activities outside of business hours or to another location.

If you have any questions about the installation or accessibility, please contact Kelsey Shipley at 604-996-5461 or kelsey@mirafloors.com. We are happy to assist with any specific accessibility requirements.

The following two tabs change content below.
Kelsey Shipley is the main writer for the MIRA Floors blog & also an account manager at Mira Floors. Have a flooring question you would like us to cover? Let me know in the comments.

Latest posts by Kelsey Shipley (see all)

Leave a Reply

Your email address will not be published. Required fields are marked *

 
WCFA ICC Greater Langley Chamber of Commerce Insurance Brokers Association CHOA Greater Vancouver Home Builders Association Better Business Bureau BCAOMA Aviva