The carpet installation for Westchester Place is now complete. Walkthroughs will now be starting. Enjoy your new carpets and the holiday season!
Buildings C & D Update – November 30th
We are on schedule to complete installation in Building C today. Tomorrow we will start installation in Building D, starting on the third floor and working down from there. Our goal is complete installation by Monday December 12.
Update – November 18th
Carpet installation in building C begins today. Installation will be completed floor by floor, starting on the 3rd floor and working down from there. We are planning to complete building C on Wednesday November 30th.
Update – November 15th
Carpet installation is complete in buildings A and B. A large bin is on site for the afternoon to take away the old carpet from those two buildings today.
Photo update
New carpet was installed in the townhome rec. room earlier this week. Here are the final results:
Installation of carpet in the hallways and lobbies is ongoing. Here are a couple of photos of the completed hallways in Building A.