We are now finished the carpet installation in Building 7171. Thank you for allowing us in your space. We appreciate your patience during the installation and looking forward to doing the installation in the final building.
Building 7171 Update July 28
Installation is moving along quickly in building 7171. Our installers expect to be complete by end of tomorrow (Tuesday).
Building 7171 Update July 25
Installation on the 1st floor is now complete. Floor prep is complete on the 2nd and 3rd floors. We are working on installation on these floors now.
Our targeted completion is early next week.
Building 7161 Complete & Building 7171 installation update
Installation in building 7161 is complete! Thank you for your patience.
Building 7171 update
Installation will start on the 1st floor working up due to prep and removal. Most prep and removal is now complete.
Building 7171 Installation Schedule
Installation Timeline for Building 7161
Please note that this timeline is an estimate and is subject to change. We will keep you updated on any changes.
Tuesday July 15- Wednesday July 16: Carpet removal on all floors. All threshold need to be removed by residents for this date.
Wednesday July 16 – Friday July 25: Carpet installation starting on 3rd floor and working down. Stairs will be installed last.
TBD: Baseboard reinstallation. We will update you as soon as a date is confirmed.
I am Kelsey Van Dam, an Account Manager at MIRA Floors. My role during the carpet installation is to make the process as smooth and pain-free as possible. If you have any concerns, feel free to contact myself or our installation manager Beth at 604-856-4799.