Building 7161 – Installation Update July 7

We are still on track to finish the installation by the end of the week. The schedule for the baseboards is still to be decided. We will update you as soon as we are aware.

 

Building 7161 – Installation update July 2nd

We have completed the carpet removal in all hallways. The crew will be finishing the subfloor preparation work today. Carpet pad installation will occur today and tomorrow.

Carpet installation will start tomorrow, starting at the top floor and working down. Once they are finished all floors, the crew will start on the stairs removal and installation. Our targeted completion date is the end of next week.

Thank you for your patience as we work in your building.